  • Process automation design & software development for (15) bioreactor/fermentor systems
  • Process automation design & software development for (6) automated centrifuge skids, design through OQ
  • Software development & commissioning for (7) CIP systems
  • Automation design, programming & commissioning of conveyor systems and product transport for blast freezers
  • Technical support for clinical production centrifugation & homogenization for (2) engineering & (12) GMP production lots
  • PLC to Delta V interfaces
  • Modifications & Upgrades to Intellution FIX SCADA systems
  • Modifications & Upgrades to Wonderware SCADA systems
  • Start-up, Trouble-Shooting, and control modifications to automated CIP Systems
  • Operational Qualification & testing of Ultrafiltration and pH neutralization systems
  • Rockwell SLC 500 PLC Software, RSLogix500 & 5000,  Rockwell FactoryTalkView, PanelBuilder MMI Software
  • Loop Processor Programming, Configuration, Testing, and Tuning
  • 3D Solids Modeling of Bioreactor systems 
  • International Commissioning & Qualification Experience
  • Kindle E-Book Author: "STEP-BY-STEP: HOW TO BRING ALLEN-BRADLEY PLC DATA INTO EXCEL"
_________________________________________________________________________________________________________

Installation, Configuration, and Testing of the following Field Instruments & Devices:

  • Process Valves ( Diaphragm & Ball ) with actuators and limit switches
  • Control Valves with I to P Transmitters
  • Coriolis, Turbine, and Thermal Mass Flow Meters
  • Pressure Transmitters
  • RTD’s and Temperature Transmitters
  • Variable Frequency Drives
  • pH and Dissolved Oxygen Probes & Transmitters
Other Services:
  • Factory Acceptance Testing
  • Site Acceptance Testing
  • System Trouble Shooting and Start-up
  • Writing of Functional Requirements Specifications
  • Writing of Detailed Design Specifications
  • P & ID’s, Instrument Lists, Component Specification, BOM, Electrical Schematics
  • Writing and Execution of Installation Qualification Documents
  • Writing and Execution of Operational Qualification Documents